Construction of Fuzhou century bright phearl organizes total design

1, project general situation
"Century bright phearl " be located in Hua Lin road and Jin Anlu to hand in collect place, it is Fuzhou company of development of beautiful continent estate invests development, build composition by 12, collect residence, office, bazaar is the omnibus village of an organic whole. Among them building of 10# ~ 12# cuts a structure for 13 casing, floor area is 10913m2, 9838m2, 10924m2 respectively, build high 24m, set the basement that join system to use room and car, autocycle to stop a garage for equipment. 2 ~ are the residence 13 layers.
1.1 construction work
Structure: This project all uses cast-in-place ferroconcrete frame to cut system of force wall construction, set two elevator holding a person and ferroconcrete stair respectively up and down, saskatoon is aseismatic fortify, basement presses design of 6 class people's air defense, each bearing grade of place Tong intensity is expressed as follows.

Member name reachs order and degree of place Tong intensity
Column a C30
2 ~ 4 C25
5 ~ carry a C20 on the head
Liang Ban 2 C25
Three-layer ~ eightfold C20

Brick wall: The wall uses 190 × of 190 × outside 90 bearing air brick, build by laying bricks or stones of M5 cement mortar is built, the wall uses Mu2.0 blame to bearing inside air brick wall.
The wall decorates outside: Bedding face is 100 × facing of face brick of 100 meters of yellow, curvilinear balcony sets baluster of ornamental design of of primitive simplicity, roofing to set shaping of inclined roofing of gules Qu Wa, complementary decorate with complex and changeful line and cylinder, make whole establish a range vivid and beautiful, .
Decorate inside: Before room, stair well, Lian Lang, vestibular ground slips to prevent floor tile, floor of the others building is floor of cement mortar building. Metope, ceiling is cement mortar inside intermediate plasterer.
Door window reachs paint: Window of all house external door uses window of door of white model steel, match virescent transparent glass, enter a door to be door of fire prevention of guard against theft, partition door of short duration is not done inside.
Roofing: Roofing is waterproof use get together amine fat film roofing of the person on thermal insulation board of built on stilts of waterproof, ferroconcrete.
Project of 1.2 water and electricity
All of 1.2.1 water system giving a platoon: A.7# building by B area frequency control is automatic water supply water supply, 4.3L/s of water supply total flow, 2.8L/s of hot water total flow. B. Cold water service pipe uses nominal pressure to be 1.6MPa, water supply PP-R heats up frit join, DN50 above valve uses flange to join. Can by sunshine aluminum foil of the bag outside the conduit of direct illuminate undertakes protective, water supply raises a canal to use means of dark apply of edge wall, floor to be brought to each to match water feature. C. The life corrupt, liquid waste is confluent, village waste pipe is emited into after classics cesspool is handled net, catchment conduit uses UPVC drain off water plastic pipe sticks adhesive bonding mouth.